Q: Pick up the incorrect statement from the following:
Option | Answer | Is Correct |
---|---|---|
1 | An activity of a project is denoted by an arrow on the net work | |
2 | The tail of the arrow indicates the start of the activity | |
3 | The arrows are drawn to scale from left to right | |
4 | Each activity consumes a given time |